• Region: Europe
  • Topics: Well Intervention
  • Date: Dec, 2024

AdobeStock 304090590Adverse weather conditions have disrupted TotalEnergies EP Danmark’s operations, delaying production from the remaining fields at its natural gas redevelopment project in the Danish sector of the North Sea.

As a result, the company has updated its timeline for achieving full production capacity at the Tyra gas field, Denmark’s largest natural gas field.

The Tyra redevelopment project has been underway since March 2024, with the first gas export from Tyra II marking the successful initial production following a major revamp. However, challenges have emerged in the process of reactivating and optimising offshore wells, particularly in relation to the reactivation of the Tyra satellite wells. These wells are critical to achieving the anticipated production plateau, and the necessary well interventions have been delayed by adverse offshore weather.

A key operational challenge arose from issues related to two transformers supplying power to essential gas compressors, which have impeded the full commissioning of the project. Despite these setbacks, TotalEnergies has made significant progress in repairing and commissioning equipment, although the anticipated timeline for full technical capacity was initially set for mid-November 2024. Uncertainties about remaining operational conditions have led to delays.

The ramp-up phase, which is closely tied to well intervention activities, has allowed for gas production to be restored from three of the six fields. However, due to weather conditions and other operational issues, the reactivation of the Tyra satellite wells has faced further delays. Offshore weather constraints, including limited weather windows, have hindered the progress of well interventions and postponed the critical reactivation of these satellite wells.

Given the current weather forecasts, the timeline for reactivating all satellite wells to achieve plateau production has been extended by approximately three weeks. The revised timeline now places the expected achievement of plateau production in the second half of January 2025.

The Tyra field is part of the Danish Underground Consortium, with TotalEnergies EP Danmark (43.2%), BlueNord (36.8%), and Nordsøfonden (20%) as the key stakeholders.

Euan Shirlaw, CEO of BlueNord, commented, “Although it is disappointing that plateau production is now expected in the new year, we are confident that the recent above-ground challenges are well understood. Once the remaining satellite wells have been reactivated, the performance of the field will no longer be constrained by weather, as has been the case during the startup phase. We look forward to reaching plateau production in January 2025 and sharing the promising results of our HEMJ program.”

TotalEnergies points out that oil and gas supply nearly 50% of Denmark’s energy needs, and once the Tyra field reaches plateau production, it is expected to contribute around 6% of the European Union's natural gas output, marking Denmark’s return as a net gas exporter.

Additionally, in June 2024, drilling operations in the Harald East area, conducted with the Shelf Drilling Winner jack-up rig, led to the discovery of additional gas condensate resources in the Harald field, which is located in shallow waters 250 km off Denmark's west coast. These new reserves could further boost production from the region, with ongoing well intervention efforts to optimise the production from the field.

 

CONTACT US

University House, 11-13 Lower Grosvenor Place, Westminster, London, SW1W 0EX
UK: 0203 411 9937

Quick Links

NEWSLETTERS

webvic-c