• Region: Australia
  • Topics: Decommissioning
  • Date: 20th November 2026

construction crane towers offshore platformDecommissioning activity in the Gippsland Basin in the Bass Strait is entering a new and crucial phase, according to Australia’s offshore regulator.

The November 12, 2026 start date on NOPSEMA’s public activity registry marked the official commencement of Campaign #1 Execution — the first physical offshore dismantling phase for the Gippsland Basin Joint Venture (GBJV).

The joint venture is led by Woodside, which assumed operatorship of the Bass Strait assets from Esso Australia in July 2026.

Campaign #1 includes the removal of the topsides of up to 13 offshore platforms, the removal of the upper jacket sections of up to 10 steel piled jacket facilities and the full removal to seabed of two monotowers, according to NOPSEMA.

Removal of the facilities is to be completed by the Allseas Pioneering Spirit heavy lift vessel, supported by various other construction support vessels.

These will transport the removed topsides and jacket sections to a sheltered location closer to shore to be transferred onto a barge or a heavy transport vessel for onward transit.

Other smaller vessels, tugs and helicopters will also provide support during the removal activities.

After delivering energy to Australia for over 50 years, many of the fields in the Bass Strait, offshore Victoria, are now reaching the end of their productive life and scheduled for decommissioning and abandonment.

The work under this first section of the decommissioning programme is expected to conclude during the first quarter of 2028, according to NOPSEMA.

The Allseas Pioneering Spirit is expected to undertake removal activities for a period of approximately five months, commencing in the third quarter of 2027.