Shell will be deploying the FPSO Gato do Mato offshore Brazil as Japan's Modec announced the completion of hull-mating work nearly a month ahead of schedule.
This comes following floating-stage hull mating and welding in October 2026, with above-water hull mating established, and a 99% acceptance rate reported in dimensional-control inspections.
Delivered as part of Modec's multi-yard modular construction services, this model is capable of removing hull construction from critical path of typical deepwater project. Supported by its signature next-generation hull (NGH) design, the model is suited for the efficient delivery of increasingly complex offshore developments.
"The team made effective use of favorable weather conditions and maintained a strong focus on quality, safety and schedule. From design and execution through to operations, every step is focused on delivering a safe and reliable FPSO, reflecting our build-to-operate philosophy. The FPSO Gato do Mato - Orca project demonstrates the distinctive value of this project execution approach and purpose-built hull design, which we look forward to presenting to our customers. I would also like to thank Shell for placing its trust in MODEC and in this approach, and for being the first customer to adopt it," said Soichi Ide, Group Head of Floating Production Solutions Business Unit / Chief Digital Officer.
A Sofec spread mooring system was deployed to support the FPSO Gato do Mato, which lies at around 2,000-meter water depth, approximately 200 kilometers south of Rio de Janeiro. The vessel boasts of a production capacity of approximately 120,000 barrels of oil per day (bopd).